Building Program

The demolition of the last building (excluding the hydrotherapy) is now complete and the compaction of special soil bought onto the site in preparation for the concrete slab is underway. 

The underground mains and power conduit have been installed with the storm water and sewerage currently being completed. Due to water inundation, over many years under the old building affecting the sub soil, a screw pile foundation will be installed before the concrete slab is installed. Currently the slab is scheduled to be poured in mid-march with the project due for handover in term 3.